OMEXOM
draws up and implements a functional tests specific
methodology, for each high voltage transformation
installation. The two-fold skill (turnkey equipment
supplier-installer) enables
OMEXOM's teams to carry out functional
trials on the complete chain, from the high voltage
gear to the control equipment.
The methodology is based on the drafting of specific
inspection procedures as a complement to the trials
carried out by the manufacturers:
 |
Visual inspection of the installations
and groundings of the low voltage cables and
equipment, |
 |
Inspection of conformity
of AC and DC power supplies and the functional
links, |
 |
Selective functional inspection,
|
 |
Test of each cable by at least
one data transmission operation. |
These tests are
carried out on the site on final completion
of the installation.
Their main objectives are:
 |
To improve the global
quality of the service provided, |
 |
To reduce commissioning
time. |
|