Présentation :

As electricity demand continues to grow in French Guiana, the territory faces a dual challenge: securing a reliable power supply while advancing its energy transition objectives. The Larivot Bioenergy Power Plant, located near Cayenne, has been designed to address both. Once commissioned, the facility will replace the existing Dégrad-des-Cannes power plant and provide 120 MW of dispatchable power.

It will strengthen energy security for the region’s main economic and population center while supporting greater integration of renewable energy into the grid.

Omexom contributed to the delivery of the high-voltage infrastructure required to connect the Larivot Bioenergy Power Plant to the EDF SEI Guyane network.

This included the construction of a high-voltage substation, the integration of seven power transformers and the installation of overhead and underground grid connections indoor modular the commissioning of critical control and protection systems, and.

A Strategic Project for French Guiana

Delivering a project of this scale requires more than technical expertise. It requires seamless collaboration across the entire electricity value chain.

By combining engineering, construction, and commissioning expertise within a single integrated approach, Omexom helped streamline interfaces, enhance coordination, and support the successful delivery of this strategic energy infrastructure project for French Guiana.

  • of guaranteed generating capacity

  • power transformers

  • high-voltage indoor modular substation

Supplying nearly half of French Guiana’s population, the Cayenne area represents the territory’s largest concentration of economic activity and electricity demand. The Larivot plant has been designed to meet these growing needs through a flexible generation model capable of adapting to fluctuations in consumption and renewable energy production.

By replacing aging generation assets with modern infrastructure, the project will strengthen grid reliability while supporting the long-term development of the territory.

Supporting the Energy Transition Through Flexible Power

The Larivot facility will run on liquid biomass, while maintaining the flexibility required to ensure system stability.

The project’s environmental commitments extend beyond renewable energy generation, encompassing biodiversity measures that protect more than 150 hectares of natural areas and help preserve local ecosystems while supporting regional development.

Combining Expertise Across the Electricity Value Chain

At Larivot, Omexom brought together specialist capabilities spanning substations, transmission infrastructure, and commissioning activities to support the successful integration of the new bioenergy plant into the electricity network.

The project illustrates how integrated expertise can help accelerate the energy transition, strengthen grid reliability, and deliver the infrastructure needed to power French Guiana’s future.

  • “VINCI Energies has mobilised several business units specialised in extra-high voltage for their know-how and expertise.”

    Adel Farouil Project Manager, Omexom Major Projects

Latest news