Nine hundred kilometers, eleven months, three business units, one team
Electrix’s (Omexom in New Zealand) wiring crews have replaced the single electrical conductor per phase with two conductors per phase, an operation known as duplexing, to increase the capacity of this transmission line from about 600MW at present, to about 1000 MW.
The project started in January 2021 and was wrapped up at the end of March 2022, with a break of four months since works could not be efficiently undertaken in the winter months. The short timeframe required a collaboration between three different Omexom New Zealand business units.
“For me, being involved with the terrific project team on such a critical project was very special. Everybody involved pulled their weight and performed extremely well. I feel privileged to have been part of such a great workforce,” said Phil Patrick.